The contractor arrived today with the framing guy to lay out the walls in the basement. They stopped by yesterday and confirmed the plan, so we're on our way.
We entirely forgot about bookshelves along the wall of the sitting room, and I gave them details on where the projector is supposed to be mounted; I think those are the only updates we have so far. They'll be loading the materials into the basement this afternoon, and the whole framing crew starts tomorrow. By thursday next week, we should be getting the electrical walkthrough to make sure that we have everything laid out properly.
Here's the empty space (look! How clean it is!) that will be the theater (on the left) and the wine cellar (right). The blue thing is the outline of where the screen will go: